dc.contributor.advisor | SYAHPUTRA, RAMADONI | |
dc.contributor.advisor | MUSTAR, MUHAMAD YUSVIN | |
dc.contributor.author | MAULANA, IKBAL | |
dc.date.accessioned | 2019-01-10T02:50:12Z | |
dc.date.available | 2019-01-10T02:50:12Z | |
dc.date.issued | 2018-12-21 | |
dc.identifier.uri | http://repository.umy.ac.id/handle/123456789/23738 | |
dc.description | Pada perkembangan zaman listrik sangatlah dibutuhkan bagi kehidupan.
PT.PLN (Persero) berusaha untuk menyuplai energi listrik seoptimal mungkin
seiring dengan semakin meningkatnya konsumen energi listrik. Dalam proses
penyaluran energi listrik mulai dari pembangkit sampai ke konsumen terdapat
banyak gangguan – gangguan. Meningkatnya jumlah beban dalam suatu sistem
tenaga listrik tentu akan menyebabkan naiknya presentasi terjadinya gangguan.
Salah satu bentuk gangguan yang dapat terjadi pada sistem tenaga listrik adalah
hubung singkat (short circuit), yang menyebabkan lonjakan arus yang disebut
arus hubung singkat. Sehinga hal tersebut yang tidak dapat dihindari.
Meningkatnya pertumbuhan industri berdampak pada bertambahnya
pertumbuhan beban dalam sistem tenaga listrik. Pertumbuhan beban tersebut
diikuti dengan meningkatnya daya reaktif akibat beban induktif pada bus beban
maupun pada saluran yang menyebabkan meningkatnya pemakaian daya reaktif.
Oleh karena itu, perlu dilakukan analisis study dalam perencanaan pemasangan
kapasitor bank untuk menanggulangi beban induktif. Pada sistem distribusi, jika
suatu jaringan tidak memiliki sumber daya reaktif di daerah sekitar beban maka
semua kebutuhan beban reaktifn dipikul oleh gardu induk yang disuplai dari
generator pada pembangkit listrik, sehingga akan mengalir arus reaktif pada
jaringan yang mengakibatkan faktor daya menurun, drop tegangan, dan
bertambahnya rugi-rugi daya. | en_US |
dc.description.abstract | In the development of the era of electricity, it was needed for life. PT. PLN
(Persero) strives to supply electrical energy as optimally as possible with the
increase in electricity consumers. In the process of distributing electrical energy
from the generator to the consumer there are many disturbances. Increasing the
amount of load in a power system will certainly cause an increase in the
presentation of disturbances. One form of interference that can occur in an
electric power system is a short circuit, which causes a surge in current called
short circuit current. So that it cannot be avoided.
Increasing industrial growth has an impact on increasing load growth in the
electric power system. The load growth is followed by increasing reactive power
due to inductive loads on the load bus as well as on the channel which causes
increased reactive power usage. Therefore, it is necessary to analyze the study in
planning the installation of bank capacitors to overcome inductive loads. In a
distribution system, if a network does not have a reactive source in the area
around the load, all reactive load needs are borne by the substation supplied from
the generator at the power plant, so that the reactive current flows to the network
resulting in decreased power factor, voltage drop, and increasing power losses. | en_US |
dc.publisher | FAKULTAS TEKNIK UNIVERSITAS MUHAMMADIYAH YOGYAKARTA | en_US |
dc.subject | Power Factor, Voltage Drop, Loss-Loss, ETAP 12.6, Capacitor Bank | en_US |
dc.title | ANALISIS PERFORMA JARINGAN DISTRIBUSI SISTEM TENAGA LISTRIK DI PT. PLN PERSERO GARDU INDUK BANTUL DAN AREA YOGYAKARTA | en_US |
dc.type | Thesis