      ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN METODE DURATION COST TRADE OFF

      Thumbnail
      View/Open
      COVER (56.87Kb)
      HALAMAN JUDUL (254.5Kb)
      HALAMAN PENGESAHAN (367.4Kb)
      INTISARI (14.00Kb)
      COVER (150.0Kb)
      HALAMAN JUDUL (351.7Kb)
      BAB III (682.2Kb)
      BAB IV (1.116Mb)
      BAB V (10.47Kb)
      DAFTAR PUSTAKA (11.13Kb)
      LAMPIRAN (142.9Kb)
      LAMPIRAN (357.5Kb)
      LAMPIRAN (234.0Kb)
      LAMPIRAN (47.77Kb)
      LAMPIRAN (71.49Kb)
      NASKAH PUBLIKASI (529.1Kb)
      Date
      2018-03-08
      Author
      HARYANTO, EKO
      Metadata
      Show full item record
      Abstract
      Project delay can be anticipated by accelerating the implementation of the project, while still considered the cost factor. The addition of resources, equipment and method will reduce time duration, but will increase the cost. The purpose of this study is analyze cost and time project arrangement by adding work time variation and employee increment then compare the result between duration and cost changing,which is more efficient. This research was conducted with the analysis of the data methods. The data used are secondary data and primary data analysis results using Microsoft Project program includes a list of material and wages, budget plan project, time schedule (curves-S), estimated time in the Microsoft Project program, data direct cost and data indirect cost. The result of this research indicated that (1) at overtime 1 hour decreased IDR 223,601,343.00 and 36,64 days duration, at overtime 2 hours decreased IDR 323,673,644.00 and 62,96 days duration, at overtime 3 hours decreased IDR 374.934.246.00 and 82,18 days duration; (2) Employee increment 1 decreased IDR 283,942,185.00 and 36,64 days duration. Employee increment 2 decreased IDR 487.920.249.00 and 62,96 days duration. Employee increment 3 decreased IDR 636.729.058,00 and 82,18 days duration ; (3) Employee increment more efficient than addition of working hours (overtime).
      URI
      http://repository.umy.ac.id/handle/123456789/20191
      Collections
      • Department of Civil Engineering

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV
       

       

      Browse

      All of UMY RepositoryCollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

      My Account

      Login

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV