      STUDI OPTIMASI BIAYA DAN WAKTU MENGGUNAKAN METODE TIME COST TRADE OFF PADA PEMBANGUNAN HOTEL WHIZ PRIME LAMPUNG

      Thumbnail
      View/Open
      COVER (57.76Kb)
      HALAMAN JUDUL (889.1Kb)
      HALAMAN PENGESAHAN (401.0Kb)
      INTISARI (86.33Kb)
      BAB I (154.3Kb)
      BAB II (953.4Kb)
      BAB III (95.68Kb)
      BAB IV (2.019Mb)
      BAB V (145.7Kb)
      DAFTAR PUSTAKA (145.7Kb)
      LAMPIRAN (1.643Mb)
      NASKAH PUBLIKASI (554.1Kb)
      Date
      2018-05-30
      Author
      SETIOBUDI, YANUAR AGUNG
      Metadata
      Show full item record
      Abstract
      The optimization of costs and time is very important to construction activities. It is used as a planning to get the best cost and time so that the optimal benefit of the project. To achieve the advantage then do steps to reach cost and time optimization such as making network project, find the critical path, calculate the duration of the project and know the amount of resources. There are several ways of achieving cost optimization in project activities, such as the addition of working hours (overtime), the addition of labor and the addition of heavy equipment (for projects that use heavy equipment). From each of these alternatives will get the results in the form of an acceleration of the same duration but the resulting costs will be different. On the research of development projects in the form of building method using time-cost trade off with two alternative calculation with addition of working hours (overtime) and additions to the labor. The addition of working hours (overtime) will be conducted in accordance with the regulations due to the influence the productivity of a worker per hour will decrease until the time of maximum overtime is 3 hours with worker productivity is at a value of 70% in addition to the that calculation is done with the help of Microsoft Project 2010 program while the addition of the labor is done by changing the overtime hours with labor so that it will not occur overtime. From the analysis conducted most optimal results are obtained with the addition of a workforce equivalent to 3 hours of overtime that is Rp.5.206.529.376,10 of the normal cost of Rp. RP.5.488.191.102,00 with a duration of the acceleration becomes 196,58 days from a normal duration is 273 days.
      URI
      http://repository.umy.ac.id/handle/123456789/20765
      Collections
      • Department of Civil Engineering

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV
       

       

      Browse

      All of UMY RepositoryCollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

      My Account

      Login

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV