      STUDI OPTIMASI BIAYA DAN WAKTU MENGGUNAKAN METODE DURATION COST TRADE OFF PADA PROYEK PEMBANGUNAN HOTEL THE KARANIE YOGYAKARTA

      Thumbnail
      View/Open
      COVER (90.65Kb)
      HALAMAN JUDUL (1.043Mb)
      HALAMAN PENGESAHAN (680.7Kb)
      ABSTRAK (156.6Kb)
      BAB I (187.5Kb)
      BAB II (388.0Kb)
      BAB III (101.8Kb)
      BAB IV (1.859Mb)
      BAB V (88.43Kb)
      DAFTAR PUSTAKA (91.25Kb)
      LAMPIRAN (301.7Kb)
      NASKAH PUBLIKASI (765.6Kb)
      Date
      2018-07-21
      Author
      SABILLA, BELADINA
      Metadata
      Show full item record
      Abstract
      In the construction project planning, time and cost greatly affect the success and failure of a project. The implementation of a construction project is a sequence of interdependent activities between one job and another.. The way in this study is to add working hours (overtime) and add labor so that the results of both will be compared. The method used is Duration Cost Trade Off Method with the help of Microsoft Project 2013 Application. From the research conducted, for the addition of overtime 1 hour decreased by Rp 174,235,266,01 and change the duration decreased 25,52 days. For 2 hours overtime decreased by Rp 245,832,845.81 and change in duration decreased 44.10 days. For the addition of overtime 3 hours decreased by Rp 284.300.094,81 and change of duration decreased 58,06 days. While for the addition of labor for 1 hour decreased by Rp 227,595,692.52 and change the duration decreased 25.52 days. For the addition of labor for 2 hours decreased by Rp 393,530,743,96 and change of duration decreased 44,10 days. For the addition of workforce for 3 hours decreased by Rp 518,173,771,93 and change of duration decreased 58,06 days. From the analysis performed the most optimal results occur when the addition of workforce for 3 hours is Rp 10.898.716.933.09 and the duration of acceleration to 91.94 days.
      URI
      http://repository.umy.ac.id/handle/123456789/22431
      Collections
      • Department of Civil Engineering

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV
       

       

      Browse

      All of UMY RepositoryCollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

      My Account

      Login

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV