      EFISIENSI BIAYA DAN WAKTU PELAKSANAAN PROYEK KONSTRUKSI DENGAN METODE CRASHING PADA PROYEK PEMBANGUNAN JEMBATAN PABELAN DI RUAS JALAN TLATAR TALUN

      Thumbnail
      View/Open
      COVER (55.31Kb)
      HALAMAN JUDUL (1.581Mb)
      HALAMAN PENGESAHAN (606.6Kb)
      ABSTRAK (10.09Kb)
      BAB I (95.92Kb)
      BAB II (408.1Kb)
      BAB III (113.0Kb)
      BAB IV (975.7Kb)
      BAB V (11.66Kb)
      DAFTAR PUSTAKA (14.35Kb)
      LAMPIRAN (393.1Kb)
      NASKAH PUBLIKASI (653.6Kb)
      Date
      2019-03-11
      Author
      SETIANINGSIH, RINI
      Metadata
      Show full item record
      Abstract
      The success of the net of a project is influenced by factors such as duration of completion of the project briefly and at a minimal cost but do not eliminate the quality elemen of the work that will be generated from the end o the job. The most common way to generate effective and efficient is to compare construction cost in the addition of heavy equipment, which needs to be noticed for expedited work is critical work. The result of this research shows that if after the addition of overtime working hours for 1 hours the cost must be Rp. 4.529.642.950,10 with the duration of 192,46 days, for additional hours overtime for 2 hours cost incurred Rp. 4.480.214.771,29 with duration of 178,50 days. For the addition of overtime for 3 hours, cost to be incurred Rp. 4.440.003.210,43 with a final duration of 167,13 days, while for the addition of heavy equipment whose duration is equivalent to 1 hour cost incurred Rp. 4.525.437.367,00 with a duration of 192,46 days, for the addition of equipments 2 hour with the cost of Rp. 4.470.569.682,67 with 178,50 days duration, then for the addition of equipment equivalent to 3 hours obtained at a cost of Rp. 4.425.902.377,53 with a duration of 167,13 days. The cost of adding heavy equipment here is more efficient than time and cost.
      URI
      http://repository.umy.ac.id/handle/123456789/30143
      Collections
      • Department of Civil Engineering

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV
       

       

      Browse

      All of UMY RepositoryCollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

      My Account

      Login

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV