      PERCEPATAN JADWAL MENGGUNAKAN SISTEM LEMBUR DENGAN PRECEDENCE DIAGRAMMING METHOD (STUDI KASUS : PROYEK PEMBANGUNAN BENDUNGAN PIDEKSO YANG TERLETAK DI KABUPATEN WONOGIRI PROVINSI JAWA TENGAH)

      Thumbnail
      View/Open
      COVER (277.4Kb)
      HALAMAN PENGESAHAN (574.6Kb)
      ABSTRAK (481.1Kb)
      BAB I (410.3Kb)
      BAB II (591.4Kb)
      BAB III (487.3Kb)
      BAB IV (1.100Mb)
      BAB V (315.3Kb)
      DAFTAR PUSTAKA (269.6Kb)
      NASKAH PUBLIKASI (1.321Mb)
      Date
      2020
      Author
      RAHAYU, FEBRI ANA DWI
      Metadata
      Show full item record
      Abstract
      In a construction project, time, cost, and quality are important things that must be considered so that delays in the project have a small percentage. The purpose of this study is to obtain the results of the analysis of the acceleration of the duration that affects the acceleration of project costs with an overtime system of 1 hour, 2 hours and 3 hours. The addition of labor is also done to be a comparison and obtain effective and optimal results. This study uses the Duration Cost Trade Off method with Microsoft Excel for data processing. The scheduling technique uses the PDM method under normal conditions obtained 5280 days duration with a total project cost of Rp 64,858,974,293.53. On the addition of 1 hour overtime hours, the duration time of 4746.1 days requires Rp 65,380,605,758.77. Adding 2 hours overtime with a duration of 4355.6 days requires a fee of Rp 66,264,119,493.23. The addition of 3-hour overtime hours with a duration of 4100.8 days requires a fee of Rp 67,107,394,957.29. The addition of 1 hour labor with a duration of 4746.1 days requires a fee of Rp 64,859,159,427.53. The addition of 2 hours overtime with a duration of 4355.6 days requires a fee of Rp 64,859,294,490.03. The addition of 3-hour overtime hours with a duration of 4100.8 days requires a fee of Rp 64,859,412,983.78. After analyzing the data, an effective and optimal value is obtained, namely the addition of 3 hours overtime with a duration of 4100.8 days requiring a fee of Rp 64,859,412,983.78.
      URI
      http://repository.umy.ac.id/handle/123456789/35551
      Collections
      • Department of Civil Engineering

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV
       

       

      Browse

      All of UMY RepositoryCollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

      My Account

      Login

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV