      STUDI OPTIMASI BIAYA DAN WAKTU MENGGUNAKAN METODE DURATION COST TRADE OFF PADA PEMBANGUNAN GEDUNG RUANG RAWAT RUMAH SAKIT UMUM KARDINAH KOTA TEGAL

      Thumbnail
      View/Open
      COVER (227.0Kb)
      HALAMAN JUDUL (377.4Kb)
      HALAMAN PENGESAHAN (120.9Kb)
      ABSTRAK (270.3Kb)
      BAB I (284.7Kb)
      BAB II (1.088Mb)
      BAB III (188.0Kb)
      BAB IV (1.467Mb)
      BAB V (178.8Kb)
      DAFTAR PUSTAKA (275.9Kb)
      NASKAH PUBLIKASI (967.7Kb)
      Date
      2018-08-24
      Author
      SYOFIANDA, MOHAMAD ZAKA ZISMA
      Metadata
      Show full item record
      Abstract
      Cost optimization and duration are really important for construction project in order to get maximum profit. Accelerating the project duration has the goal to avoid the delay of project’s completion. This delay would cause the contractors to get sanctions in the form of fine as agreed upon in the contract. Daily fine because of project’s delay is 1% of the contract. The most used maximum working hours (overtime) is 3 hours. Addition of working hours (overtime) must meet the regulations as workers productivity in general will decrease every hour. In order to analyze the data in this research, the program that is being used is Microsoft Project 2010 with the method duration cost trade off. The Microsoft Project 2010 program will generate a critical path and cost rising as an addition of working hours (overtime). The method of duration cost trade off will generate the acceleration of the duration and cost rising because of the duration has been accelerated in every work. The analysis that has been done gain a result the most optimum way is by adding 3 hours of overtime which is Rp.7.262.868.225,04 from the normal cost Rp.7.543.474.717,98. The acceleration of the duration becomes 155, 04 days from the normal duration which is 204 days. The difference of the cost is Rp.204.759.45, 93 and the difference of the duration is 48, 96 days.
      URI
      http://repository.umy.ac.id/handle/123456789/22481
      Collections
      • Department of Civil Engineering

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV
       

       

      Browse

      All of UMY RepositoryCollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

      My Account

      Login

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV