      ANALISA PENGENDALIAN DURASI DAN BIAYA KONSTRUKSI PEKERJAAN JALAN DI SUMATRA SELATAN DENGAN METODE DURATION AND COST TRADE OFF

      Thumbnail
      View/Open
      COVER (47.86Kb)
      HALAMAN JUDUL (641.5Kb)
      HALAMAN PENGESAHAN (385.3Kb)
      ABSTRAK (183.4Kb)
      BAB I (294.5Kb)
      BAB II (1.330Mb)
      BAB III (189.6Kb)
      BAB IV (837.4Kb)
      BAB V (10.86Kb)
      DAFTAR PUSTAKA (290.4Kb)
      LAMPIRAN (1.441Mb)
      NASKAH PUBLIKASI (692.2Kb)
      Date
      2019-02-22
      Author
      PRABOWO, UTMAN DWI
      Metadata
      Show full item record
      Abstract
      Infrastructure development in Indonesia has experienced a significant development. This fact is reflected in the increasing development both in the road sector and other infrastructure facilities. A project that is carried out will always have a high risk, this high risk is the basis of why a planning and implementation in the completion of the project work Development of the Improvement of Simpang Kabu Danau Raya Cross 5 Nimbung Road in southern Sumatra must be carried out properly and carefully. The purpose of this study is to compare the duration and cost of normal projects with duration and costs due to additional working hours and heavy equipment capacity with Duration and Cost Trade Off Method. From the study shows that the costs incurred for the addition of working hours (overduration) for 1 hour is lower than the normal price of Rp. 24,357,189,241.49 with an acceleration of 152 days, for the cost of additional working hours (overduration) for 2 hours is Rp. 24,343,782,305.97 with an duration of 141 days, for the cost of additional work (overduration) 3 hours is Rp. 24,174,857,220.56 with a duration of 128 days acceleration. And while for the addition of labor / heavy equipment for 1 hour the cost of Rp. 24,250,887,151.06 with an acceleration of 152 days, for the addition of labor / heavy equipment for 2 hours the costs incurred were Rp. 24,136,016,372.69 with an acceleration duration of 141 days, and for the addition of labor / heavy equipment for 3 hours. the amount needed is Rp. 24,002,792,329.40 with a duration of 128 days. It can be concluded that the acceleration of the duration of the project with the addition of working hours (overduration) or the addition of labor / heavy equipment is more effective and efficient in terms of cost and duration compared to the normal costs and duration of the project.
      URI
      http://repository.umy.ac.id/handle/123456789/29168
      Collections
      • Department of Civil Engineering

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV
       

       

      Browse

      All of UMY RepositoryCollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

      My Account

      Login

      DSpace software copyright © 2002-2015  DuraSpace
      Contact Us | Send Feedback
      Theme by 
      @mire NV