STUDI OPTIMASI BIAYA DAN WAKTU MENGGUNAKAN METODE DURATION COST TRADE OFF PADA PROYEK PEMBANGUNAN QUEST HOTEL YOGYAKARTA
Abstract
The time, quality, and cost are three important greatly affect the success
and failure of a project. A project was implemented by the pre-planned cost and
duration, but implementation often not in accordance with what has been
planned. The purpose of this research is to calculate the cost change way to add
working hours (overtime) and add labor so that the results of both will be
compared. Data analysis is used Duration Cost Trade Off Method with the help of
Microsoft Project 2013 Application. From the research conducted, for the
addition of overtime 1 hour decreased by Rp 216,766,289.01 and change the
duration decreased 122.43 days. For 2 hours overtime decreased by Rp
357,484,452.58 and change in duration decreased 94.05 days. For the addition of
overtime 3 hours decreased by Rp 457,231,827.72 and change of duration
decreased 73.19 days. While for the addition of labor for 1 hour decreased by Rp
227,406,477.40 and change the duration decreased 122.43 days. For the addition
of labor for 2 hours decreased by Rp 390,751,942.47 and change of duration
decreased 94,05 days. For the addition of workforce for 3 hours decreased by Rp
510,760,033.11 and change of duration decreased 73.19 days. From the analysis
performed the most optimal results occur when the addition of workforce for 3
hours is Rp 510,760,033.11 and the duration of acceleration to 73.19 days.