STUDI OPTIMASI WAKTU DAN BIAYA DENGAN METODE TIME COST TRADE OFF PADA PROYEK KONSTRUKSI PEMBANGUNAN JEMBATAN KALI KABUYUTAN
Abstract
The success of a project can be seen from a short duration and small cost.
A project managed systematically so that the timing of the work can be
ascertained to be the same as planned or can be accelerated from the estimate, so
that the cost do not exceed the budget and avoid any fines due to the delay of
completing the project. The aim of this study to get the result from acceleration of
duration so that the researcher know cost change project with enhance working
hours (working overtime) and enhance some equipment. Then compare to get
more effective result. The data analysis used Microsoft project 2010 program and
time cost trade off method. The result of this research get the duration 147 days
in normal condition with spent a normal cost Rp.1.169.719.631,00, working
overtime 1 hour during the project spent 129,46 days with total cost Rp.
1.151.448.867,04, working overtime 2 hours during the project spent 115,50 days
with total cost Rp. 1.146.692.609,70, and working overtime 3 hours during the
project spent 104,13 days with the total cost Rp. 1.142.818.828,58. The additional
equipment equal with 1 hour working overtime and spent 129,46 days with the
total cost Rp. 1.131.937.122,36, The additional equipment equal with 2 hours
working overtime and spent 115,50 days with the total cost Rp. 1.105.698.013,12,
and the additional equipment equal with 3 hour working overtime and spent
104,13 days with the total cost Rp. 1.084.335.943,78. Therefore, the cheapest cost
with the fastest duration found in the additional equipment equal with 3 hour
working overtime with duration of 104,13 days and cost of Rp. 1.084.335.943,78.