IDENTIFIKASI RISIKO KETERLAMBATAN PADA PROYEK PEMBANGUNAN GEDUNG SEKOLAH SMA MUHAMMADIYAH 3 YOGYAKARTA
Abstract
Development in various fields is an effort to create prosperity and
prosperity for the people. Therefore, the results of development must be enjoyed
by all people in a fair and equitable manner. With the development dexterity,
companies began to work as executors and planners. This is motivated by hopes
of gaining huge profits. Delays in construction projects can be caused by errors in
estimating the time needed to complete the project in the planning stage or
several possibilities, for example, improper management, problems of material,
labor, equipment, finance, and environment that do not support so that project
implementation is hampered , and will result in project delays. In the construction
project of the Muhammadiyah 3 School Building in Yogyakarta, there are several
factors that hinder the completion of the project, therefore a study is needed to
identify and analyze the factors that influence project delays. The method used in
this study is the collection of primary and secondary data referring to the
questionnaire form and checklist form. The results of the research conducted, the
potential for events that have a high level of risk are 1) Work floor work; 2)
Foundation work; 3) The work of talud, pile and fence. Based on the average
value of risk, it is known that the work that has the highest risk level of delay is
lower structure work with an average risk value of 8.95. This happens because of
unstable soil conditions and design changes in the foundation sub-work resulting
in delays in work and work experiencing repetition.