KAJIAN FAKTOR RESIKO KETERLAMBATAN PADA PROYEK PEMBANGUNAN JEMBATAN DI BENDUNG KAMIJORO
Abstract
Risk management is a science to identify and assess the potential risks that
occur in a project. A risk is an event that may occur accidentally in a project. Risk
is associated with possibilities or probabilities that occur beyond expectations.
The implementation of the construction of bridge construction of bridge
contruction projects, in general, can experience many risks, one of the risks that
occur is the delay in work. This study aims to identify and assess risk factors that
can cause delays in a job and identify jobs that have the highest risk of delay in
the project. To identify potential events and impacts on each work carried out
using the Work Breakdown Structure (WBS) and interviews, then it can be
processed using the risk = event x impact approach and the results can be
described by Risk Matrix. Then determine the critical path with network planning.
The results of the risk assessment indicate that the work that has the highest level
of risk of delay is the work of the bridge floor with an average risk value of 8.1
and weir body work with a mean risk value of 6.7.